Civic Centre Resource Library – Sept. 25

Things are really shaping up at the Civic Centre Resource Library this week. The exterior sheathing installation continues at the south side of the building. Glazing installation is ongoing around the exterior perimeter as well. Fritted glazing installation along the north and west are also being installed. Check out some photo updates.

View of south elevation. Hardscaping and sheathing are ongoing.

Framing work is ongoing at the main entrance.

Interior insulation and framing are ongoing at the music and control rooms.

Frit glazing installation is ongoing.

Staircase construction is ongoing.

 

 

 